Mechanic's Liens - Friday's Free Form - Notice of Intent to Lien - General Contractor

Licensed general contractor massachusetts

How many times have you been in this situation: You are owed money on a construction project and are thinking of filing a mechanic's lien. But you know that after filing it there will begin a serious dispute process, and probably involving the hiring of lawyers on each side. You would like to send a notice to the other side telling them that if it is not paid, more serious steps will be taken. Well, there is a form to be used in this situation. In my experience, this is a very popular form--so much so we would like to make it available to the construction industry.



This form below warns the owner that you will be filing a mechanic's lien if payment is not made within ten days. Hopefully, it will create a serious dialogue for settlement. Come up with your bottom line amount to settle and be prepared to offer it to the owner if he or she is negotiating in good faith. Remember that the last thing an owner wants is a lien on their property: it jeopardizes title, interferes with their relationship with the construction lender, and prevents refinancing or sale. This Notice is worded in a non-threatening manner so as to capitalize on this situation, with the owner knowing that you are required by law to file a lien within a set period of time or lose your lien rights.

WHO CAN USE THIS FORM? All persons, whether general Licensed general contractor massachusetts , subcontractor, or supplier.

HOW TO SERVE: There is no need to file this with the court or record with the recorder's office. It is simply served by mailing.

WHO TO SERVE: If you are a general Licensed general contractor massachusetts , serve the owner and construction lender. If you are a subcontractor or supplier, serve the owner, general, and construction lender.

HOW TO SERVE: Although not required, it is recommended for its effectiveness to be served by certified mail.

WHEN: Serve ten days before you file or record the mechanic's lien. Remember, it does not extend the time to file a mechanic's lien.



Tag : Licensed general contractor massachusetts

1 টি মন্তব্য:

  1. Dear admin,

    Building permits range from electrical, plumbing, gas, well, septic, fireplace installation, finishing a basement and the list goes on. While building permits can be a major pain for both contractors and homeowners, they are meant to actually protect the general public against shoddy construction and inadequate materials that aren't up to code.
    about more : Excavation Company Massachusetts

    Thank you for read my comment.

    Regards
    alfajripon